SERIES: Independent low Cabinet

 

NEW DWG. NO. OLD DWG NO. TYPE-LAYOUT CAPACITY IN METER POSITIONS TOTAL LOAD CAPACITY PROVISION FOR  PHOTOVOLTAIC CELLS MAIN USE
7540014 -1TQ/252-1Along road-Meter towards road1 - 3phase100 ANO1 independent house
7540014 -2TQ/252-2At right angles to road-Service to the right1 - 3phase100ANO1 independent house
7540014 -3TQ/252-3At right angles to road-Service to the left1 - 3phase100ANO1 independent house
7540014 -4TQ/252-4Along road- Meter towards the house1 - 3phase100ANO1 independent house
7540014 -5TQ/252-5Along road-Meters towards the house2 - 3phase + Receiver2X100AYES1 independent house
7540014 -6TQ/252-6At right angles to road-Service to the right2 - 3phase + Receiver2X100AYES1 independent house
7540014 -7TQ/252-7At right angles to road-Service to the left2 - 3phase + Receiver2X100 AYES1 independent house
7540014 -8TQ/252-8Along the road Meters towards house2 - 3phase + Receiver2X100 AYES1 independent house
7540014 -9TQ/252-9Along the road-Meter towards road1 - 3phase + Receiver100AYES1 independent house
7540014 -10TQ/252-10At right angles to road-Service to the right1 - 3phase + Receiver100AYES1 independent house
7540014 -11TQ/252-11At right angles to road-service to the left1 - 3phase + Receiver100AYES1 independent house
7540014 -12TQ/252-12At right angles to road -Meter towards house1 - 3phase + Receiver100AYES1 independent house
7540014 -13TQ/252-13Back to Back for two houses - equal2 - 3phase + Receiver per house200ANO2 adjacent houses
7540014 -14TQ/252-14Back to Back for two houses - equal2- 3phase per house2X100ANO2 adjacent houses

7540014 -15

 

 

TQ/252-15Back to back for two houses - unequal3phase + Receiver per house2X100AYES2 adjacent houses
7540014 -16TQ/252-16Back to back for two houses - unequal2- 3phase per house2X100AYES2 adjacent houses
7540014 -17-Along road-Meter towards road1- 3phase 80ANO1 independent house
7540014 -18-Along road-Meter towards road2 - 3phase + Receiver80AYES2 adjacent houses
​7540014-19

​-
​Pedestrian Light Controlled Crossing

​Meter Cabinet
​3x100
​NO
Pedestrian Crossing

 

COMMENTS

  • ONE THREE PHASE METER OCCUPIES TWO EQUIVELANT METER POSITIONS (SINGLE PHASE)
  • ONE METERING PANEL (ELECTRIC LOAD>100A) OCCUPIES SPACE OF 80CM WIDTH AND 120CM HEIGHT
  • ON THE METER BOARD A SPACE MUST BE PROVIDED FOR 2-3 EQUIVELANT METER POSITIONS FOR EAC (TARIFF RECEIVERS)
  • FOR STORAGE RADIATORS A 3 PHASE METER IS REQUIRED (TWO EQUIVELANT SINGLE PHASE) + 1 POSITION FOR RECEIVER
  • FOR ELECTRICAL LOADS > 300 KVA MODIFICATIONS TO THE TYPICAL PLANS REQUIRED - COMMUNICATION WITH EAC

 

 

​​